View Work Estimate

Estimation Type Original Estimation
Approved Estimation Test Project 20-03-2017
Plan/Non-Plan New S.R Work
Project Name Test Project 20-03-2017
Region North Region
Circle Delhi
Sub-Circle Qutub Minar Sub Circle
Monument Anceint Mosque
Financial Year 2017-2018
Sub Head Of the Work Minor Work
Rate Analysis By ASI
Report Summary Item 1
State
Head Plan
Funded By
Estimate Framed By test
Estimate Approved By test
Estimate Checked By test
Estimated Cost 2,000,000
Picture
    Document not uploaded
Drawing
    Document not uploaded
Inspection Performed By
Date of Visit 03-20-2017
Time 10:15
Inspection Summary test
Inspection upload document
    Document not uploaded
Completion Report
    Document not uploaded
Estimated Start Date 03-20-2017
Estimated End Date 03-20-2017
Completion Approved by
Actual Labor Cost
Tendering Misc Charges
Total Expenditure 2000000.00
Approval Status Pending