Project Name Repairs to Temple of Aishwar at Sinnar, Dist. Nasik.
Financial year 2017-2018
RCP Amount 500,000
Plan/Non Plan
RCP provision for current year Ongoing work
Region West Region
Circle Aurangabad
Sub Circle Bibi-ka-Maqbara Sub Circle
Monument Temple of Aishwar, District Nasik
Item to be executed Construction of retaining wall and support wall including earth work excavation, cement concrete in 1:3:6, constructing UCR masonry, recess pointing, filling murum soil as back filling, removing and re-plastering at roof in lime plaster, stone flooring for platform, apron and approach pathway etc…
Additional RCP? No
VIP References
    Document not uploaded
RCP-Before Pictures
    Document not uploaded
RCP Video
    Document not uploaded
Other Documents
    Document not uploaded
Current Status Approved